Crane unloading: who slings the load?

When unloading by crane, several people work together: one operates the crane, one slings the load, one receives it at the set-down point. In Germany, DGUV principle 309-003 describes selection, instruction and proof of competence for crane operators; DGUV information 209-013 on slingers gives guidance on slinging. Who takes which role should be settled before delivery.

What matters

Crane operator
Trained, instructed and appointed – on a crane truck usually the partner's driver.
Slinger
Appointed by the company, knows lifting gear and load behaviour.
Lifting points
Only the points and anchors provided by manufacturer or plant.
Set-down point
Someone guides and receives the load.

Planning questions

We clarify these points before quoting – the earlier they are known, the more precise the plan.

  1. Who slings on site?
  2. Which lifting gear is needed?
  3. Where are the lifting points on the pieces?
  4. Who guides at the set-down point?

What we need from you

  • Pieces with lifting points
  • Lifting gear needed
  • Responsibilities
  • Contact

Preparation: Installation, fitting and distribution inside the building are done by your team. We deliver to the agreed, accessible unloading point – unloading scope, waiting time and returns are set out in the quote.

What we do for you

What we organise

  • Transport of building materials and elements within standard limits – from plant or merchant to site
  • Delivery in the agreed slot, with notice and a fixed contact
  • Crane truck, truck-mounted forklift or inloader can be organised via partners, by arrangement

Good to know

Transport racks, lashing points and lifting points are not the same thing. Lift only at points intended for it.

How it works

  1. 01

    Request

    You send collection point, site, date and load details using the form below – anything unknown can stay open.

  2. 02

    Review

    We clarify in advance who slings, which gear is needed and who receives the load.

  3. 03

    Quote

    You receive a quote with a clear scope: transport, delivery slot, unloading and any return runs.

  4. 04

    Execution

    Crane unloading with defined roles, set-down at the agreed point.

Questions and answers: Crane unloading: who slings?

Does the truck driver sling the load?

Not automatically. Who slings is agreed beforehand – your staff or the crane partner's.

What rules apply to crane operators in Germany?

Crane operators must be suitable, instructed and appointed. DGUV principle 309-003 describes selection, instruction and proof of competence.

Who provides the lifting gear?

We clarify that per order. For precast elements, plant and manufacturer specify which gear and points to use.

Request

Request for this topic: Crane unloading: who slings?

Three steps. Anything you do not know yet can be left open.

Details for planning

  • Pieces with lifting points
  • Lifting gear needed
  • Responsibilities
  • Contact

Prefer to talk directly?

+49 30 346 467 850info@logisticoo.comMon–Fri 8am–6pm Berlin time (CET/CEST)

Route and delivery date

Collection
Construction site

We check every route and come back with a proposal.

Delivery date
Is there a fixed delivery time window? (optional)

What is being delivered?

Dimensions of the largest piece (L × W × H)
Total weight
Unloading at the site

We check per request what is possible at your site.

Access to the site (optional)

You can send site plans, load lists or photos of the access after our first reply.

Contact and review

Anything that matters for planning.

Your details at a glance

Please review your details. “Edit” takes you back to the step; nothing is lost.