Delivering precast stairs and balcony slabs

Stair flights, landings and balcony slabs are compact, heavy precast pieces with visible faces and cast-in parts. They are placed one by one by crane – usually when the floor is ready. For transport, support and anchors per plant specification and protection of edges and treads are what count.

What matters

Supports
Supported on timbers at the points set by the plant.
Anchors
Lift only at the intended transport anchors.
Visible faces
Protect tread nosings and fair-faced concrete from spalling.
Single placing
Each piece is a separate crane lift.

Planning questions

We clarify these points before quoting – the earlier they are known, the more precise the plan.

  1. Which pieces, with weights?
  2. Where are supports and anchors?
  3. When are they placed?
  4. Site crane or crane truck?

What we need from you

  • Parts list with weights
  • Plant data on supports and anchors
  • Installation date
  • Lifting options

Preparation: Installation, fitting and distribution inside the building are done by your team. We deliver to the agreed, accessible unloading point – unloading scope, waiting time and returns are set out in the quote.

What we do for you

What we organise

  • Transport of building materials and elements within standard limits – from plant or merchant to site
  • Delivery in the agreed slot, with notice and a fixed contact
  • Crane truck, truck-mounted forklift or inloader can be organised via partners, by arrangement

Good to know

Tell us the heaviest piece and the distance to its final position – that determines whether the site crane is enough or a crane truck is needed.

How it works

  1. 01

    Request

    You send collection point, site, date and load details using the form below – anything unknown can stay open.

  2. 02

    Review

    We check weights, supports and lifting options and plan vehicle and date.

  3. 03

    Quote

    You receive a quote with a clear scope: transport, delivery slot, unloading and any return runs.

  4. 04

    Execution

    Loading per plant specification, transport, delivery for the installation date, handover from the vehicle.

Questions and answers: Precast stairs and balconies

How are precast stairs secured?

On timbers at the plant's support points, with straps and edge protection so the tread nosings carry no load.

Can a crane truck lift the stair directly into place?

If weight, distance and standing position fit, yes – crane trucks can be organised via partners. We check each case.

Do you deliver balcony slabs together with stairs?

Yes, if dates and lifting order fit. We plan the loading sequence by installation.

Request

Request for this topic: Precast stairs and balconies

Three steps. Anything you do not know yet can be left open.

Details for planning

  • Parts list with weights
  • Plant data on supports and anchors
  • Installation date
  • Lifting options

Prefer to talk directly?

+49 30 346 467 850info@logisticoo.comMon–Fri 8am–6pm Berlin time (CET/CEST)

Route and delivery date

Collection
Construction site

We check every route and come back with a proposal.

Delivery date
Is there a fixed delivery time window? (optional)

What is being delivered?

Dimensions of the largest piece (L × W × H)
Total weight
Unloading at the site

We check per request what is possible at your site.

Access to the site (optional)

You can send site plans, load lists or photos of the access after our first reply.