Standard load or abnormal load?

Whether an element travels normally or as an abnormal load is decided not by its name but by the loaded vehicle: width, height, length, total mass and axle loads. In Germany the general maximum width is 2.55 m and the maximum height 4.00 m (section 32 StVZO; vehicle and load together: section 22(2) StVO). Above that a permit under section 29(3) StVO is needed or – if the load projects – an exemption under section 46(1) no. 5 StVO; which decisions are required depends on the case. A twin wall can travel within standard limits – or, if it stands tall, not.

What matters

The vehicle counts
Vehicle and load together decide, not the element alone.
Width and height
In Germany generally 2.55 m width and 4.00 m overall height.
Length and weight
Length, total mass and axle loads can set the limit too.
Permit
Above the limits: permit from the responsible road traffic authority.

Planning questions

We clarify these points before quoting – the earlier they are known, the more precise the plan.

  1. What are the dimensions of the largest piece – upright or flat?
  2. How heavy is it?
  3. Can it be loaded differently to stay within limits?
  4. Is the piece divisible?

What we need from you

  • Dimensions of the largest piece
  • Weight
  • Loading method
  • Route

Preparation: Installation, fitting and distribution inside the building are done by your team. We deliver to the agreed, accessible unloading point – unloading scope, waiting time and returns are set out in the quote.

What we do for you

What we organise

  • Transport of building materials and elements within standard limits – from plant or merchant to site
  • Delivery in the agreed slot, with notice and a fixed contact
  • Crane truck, truck-mounted forklift or inloader can be organised via partners, by arrangement

Good to know

We organise scheduled transport of building materials and elements within the permitted vehicle, load and weight limits. If a shipment needs heavy or out-of-gauge transport because of its dimensions or loads, we plan it separately as an abnormal load.

How it works

  1. 01

    Request

    You send collection point, site, date and load details using the form below – anything unknown can stay open.

  2. 02

    Review

    We check dimensions, weight and possible loading methods and tell you whether it stays within standard limits.

  3. 03

    Quote

    You receive a quote with a clear scope: transport, delivery slot, unloading and any return runs.

  4. 04

    Execution

    Within limits: normal transport. Above: separate planning as an abnormal load with a permit.

Questions and answers: Standard or abnormal load?

From what width does a truck in Germany need a permit?

When vehicle and load exceed the general maximum width of 2.55 m under section 32 StVZO and section 22(2) StVO (vehicle and load). A permit or exemption from the road traffic authority is then needed – for example under section 29(3) StVO or, if the load exceeds the dimensions, under section 46(1) no. 5 StVO; which decisions are required depends on the case.

Is a transport below these dimensions always permit-free?

Not necessarily. Length, weight and axle loads count too, and work in the street – such as a crane or stopping in front of the site – may need an official order.

Do the same limits apply in other countries?

Not everywhere. Limits differ by country; we check them for your route.

Request

Request for this topic: Standard or abnormal load?

Three steps. Anything you do not know yet can be left open.

Details for planning

  • Dimensions of the largest piece
  • Weight
  • Loading method
  • Route

Prefer to talk directly?

+49 30 346 467 850info@logisticoo.comMon–Fri 8am–6pm Berlin time (CET/CEST)

Route and delivery date

Collection
Construction site

We check every route and come back with a proposal.

Delivery date
Is there a fixed delivery time window? (optional)

What is being delivered?

Dimensions of the largest piece (L × W × H)
Total weight
Unloading at the site

We check per request what is possible at your site.

Access to the site (optional)

You can send site plans, load lists or photos of the access after our first reply.

Contact and review

Anything that matters for planning.

Your details at a glance

Please review your details. “Edit” takes you back to the step; nothing is lost.